Camping Magazine, Jan, 2002 by Rick Stryker
Whether you're planning to tackle needed facility repairs in house or whether you're going to contract the work out, the first few steps may well determine the success of the final product. Using several examples, we illustrate how careful, methodical planning eases the administration of the project, no matter who is doing the work.
Needed Repairs
Assume that there is already a comprehensive list of needed repairs. Often, creating this list is a very arduous and contentious process which, once complete, most staff would prefer not to revisit. And although the expected cost of each need is a critical element in the preparation for the repairs, the initial pass in the prioritizing process should be made based on the operational or programmatic needs, outside the realm of cost. Once estimated costs have been tabulated, the list should then be reviewed and revised and all of the projects prioritized within the framework of the overall budget.
Taking Stock of Conditions
Once we have a list, the next step is to take stock of the conditions that need to be repaired or considered for replacement. Most importantly, the causes of the deterioration need to be uncovered. This need not be a long, drawn out forensic investigation, but to address symptoms of a problem without looking for a cause is short sighted at best.
For example, there is a potential host of causes for bathroom floors to fail, including a leaking seal at the toilet joint, a lack of or poorly installed floor drain, undersized shower curtains, or sloppy camper showering. Even condensation on the tank and bowl of a toilet can cause a subfloor to fail. In addition, conditions under the building such as a poorly drained or ventilated crawlspace can cause condensation to form -- soaking insulation and keeping the underside of the floor saturated. A thorough check and some careful fore-thought about the damage to be repaired -- the "symptom" so to speak -- not only helps to ensure a lasting repair, but also ensures that the planned project scope is sufficiently thorough. This reduces the likelihood for surprises and cost overruns after the project is under way.
Understand that there is a break-even point associated with any repair. A certain situation might be causing accelerated deterioration, but the solution may be so cost prohibitive that you may decide that you can accept a shorter life span for a project. For example, if the floor is rotting because of tank condensation dripping, one solution could be that a small hot water feeder line be connected to the tank water supply. By adding just a little warm water to the tank water, the porcelain won't stay cold, and the humidity won't condense. However, if this toilet is in a location without hot water, or the plumbing is inaccessible, it may be more acceptable to look at replacing the floor, putting down a single sheet of vinyl and using additional caulk to reduce the amount of condensation that is getting to the subfloor.
Materials Required
When the cause of the problem has been determined, the next step is to begin to assemble the materials list by taking measurements and creating a table of items and the required quantities. In this article, we'll look at a simple roofing project for a small building, and we'll assume that the staff you plan to use has the knowledge and experience for the project. (That assessment is another column altogether!) This has to be done with standard units in mind. The physical dimensions of the project, and therefore the amount of material purchased, is a significant factor in the cost of the project. This is particularly true with smaller projects where a small amount of many different materials are required. In our bathroom flooring example above, if we are replacing a subfloor, it is not enough to know that we have to replace a 5/8-inch plywood subfloor in a 7-by 7-foot (49 square feet) bathroom. Plywood comes in 4- by 8-foot sheets. Only 48 square feet - total - are available in each sheet. This project requir es two sheets of plywood, doubling the cost of this particular material. Even if the total square footage is slightly less than the available 48 square feet, there is likely to be some waste when the sheet is cut. The more irregularly shaped the floor, the more cuts, the more waste, and the greater possibility that a single sheet won't cover the project.
While we're on the subject of units, it's important to understand that construction measurement has a language and lingo all its own. When assembling the "shopping list" for any project, make sure that each item is delineated in appropriate units. For example, on road projects, the materials purchased from a quarry or asphalt plant are likely to be sold by the ton. The commercial paving contractor, however, is likely to charge by the square yard, based on a certain thickness of each material. The savvy facility manager and director are familiar with the relationship between the different units, and are prepared to use the right term with each audience. In our roofing example, the contractor's unit is typically the "square" or 100 square feet. The roof itself is 28 feet long and 12 feet from the edge to the ridge or 28- by 12-feet which equals 336 square feet on each side - 672 square feet total or nearly 7 square.